Project Experience > Demolition > Panasonic Cardiff
Panasonic Cardiff

Contract Details

  • 20 week programme
  • General site clearance and removal of hard surfaces
  • Services disconnections
  • Demolition of 3 factory buildings, offices and boiler house
  • Disposal of asbestos and hydrocarbons contamination
  • Break up and crushing of 30,000m2 of reinforced floor slabs and foundations
  • Turnover and compact to depths up to 2m – 48,000m2
  • Re-grade site with crushed materials to balanced levels – 62,000m2
  • Break up and crush existing roads and external slabs – 25,000m2
  • Staged release of site to Client for ongoing use
 
Client – Persimmon Homes
Value – £800,000
Duration – 2005-2006