Walters UK Ltd logo
Project Experience > Landfill > Lamby Way Landfill Site Works
Lamby Way Landfill Site Works

Contract Details

  • The Cardiff City Council Lamby Way Landfill Site is located on the Severn Estuary foreshore southeast of the city.
  • It covers an overall area of 50 hectares, part of which has been filled to capacity.
  • In order to increase the capacity of the site and to meet current environmental standards, the Council has embarked on a programme of works to cap the filled part of the site and to open up more cells for further landfill.
  • Under the Phase I Contract, a 15 hectares area of completed landfill was reprofiled and then capped with a 150mm protection layer of soil, upon which were successively laid a geotextile membrane, a 1mm thick HDPE membrane and an HDPE drainage layer. Finally, the area was overlaid with a final capping of 800mm of sub soil. At the same time, vertical landfill gas extraction pipes and leachate drains and outfalls were installed.
  • Under Phase II, a separation layer was installed between the previously filled part of the site, to which it in effect formed a capping layer, and a new adjacent landfill cell. In addition to the layers provided in the capping Phase I, a 750mm-clay layer reinforced with a geogrid was incorporated in the separation layer.
  • Phase III comprises of the construction of a new cell to extend the landfill capacity of the site. In addition to the installation of the separation layers, which included a 500mm thick geogrid reinforced clay layer; the work involved the excavation of 70,000m3 of material to increase the available capacity of the cell. Part of this excavated material was used in forming the reinforced clay layer.
 
Client – Cardiff County Council
Value – £5.3 million
Duration – 1997-1998